Site selection or lot purchase.
-
Order preliminary design blueprints.
-
Select construction procedure, owner builder, project manager or contractor.
-
Pre qualify for financing and establish preliminary budget.
-
Obtain required permits.
-
Site preparation.
-
Obtain on site utility, well drilling, and septic plan and permits.
-
Submit preliminary blueprints to sub contractors as required for bids
-
Blue print changes made and final plans approved by owner.
-
Review budget and make changes as required.
-
Submit final plans for financing and permits.
-
Letter of commitment for financing and all permits approved.
-
Order IHC building package.
-
Order any additional required materials.
-
Plot plan surveyed (as built) and foundation, utilities installed.
-
IHC package arrives at site.
-
First stage construction of weather tight shell begins.
-
Rough-in plumbing and electrical
-
Framing, electrical, plumbing inspections as required.
-
Interior finishes completed and inspected.
-
Landscaping as required, weather permitting.
-
Move in.
|